Construction Web guide: infrastructure, buildings, engineering, architectureThelen Reid Brown Raysman & Steiner
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About Thelen ConstructionWebLinks Contact Us

Public-Private Partnerships
Private Financing of Infrastructure in California: Overview of PPP Opportunities and Challenges

'Material Effect'
U.S. Supreme Court Clarifies Proof Needed to Impose False Claims Act Liability on Subcontractors

Got Early Completion
Owner’s Oral Promise to Pay Subcontractor Enforced by Massachusetts Court

Block Claims of Waiver
When Loans Go Bad, Pre-Workout Agreements Allow Lenders to Protect Their Rights While Negotiating

Bankruptcy Code Is No Bar
Bankrupt Sub’s Claim Against General Contractor Is a Non-Core Proceeding and Must Be Arbitrated, U.S. Court Holds

Saves Time
Prequalification in Government Construction Contracts: How It Works, How Disputes Are Resolved

Fabrication, Design Cases
U.S. Court Permits Quantum Meruit Claims for Work Not Controlled by Contract

No Own Work Exclusion
Florida, South Carolina Supreme Courts Hold that Contractors’ CGL Policies Cover Damages Arising from Subs’ Defective Work

Previous Issues

Construction Industry News

Termination for Default Justified If Contractor Does Not Respond to a Well-Founded Notice to Cure


April 9, 2001


Back to Industry Newsletters
 

Thelen Reid Brown Raysman & Steiner LLP

The Navy contracted with AEC Corp. to complete the construction of a training center. During construction, AEC fell behind schedule. The Navy issued a cure notice in December 1990. In January 1991, the parties agreed to a new schedule and moved the completion date for the project to April 1991. The Navy agreed not to terminate the contract for default if AEC continued to make progress according to the new schedule.

In March 1991, the Navy sent AEC another cure notice. In the notice, the Navy stated that its prior agreement not to pursue termination for default was contingent upon AEC's diligently pursuing completion of the contract by April. Based on the AEC's declining project staffing, the Navy expressed concern about AEC's ability to complete the project on time and advised that, unless that condition was cured within 10 days, the Navy would consider terminating the contract for default.

AEC responded to the cure notice by blaming its poor performance on the government for changes and delays. AEC also stated that its surety was maintaining a "financial stranglehold" by not releasing funds for construction, and that if this continued, it would be doubtful that AEC could complete the project. The Navy responded by asking AEC to "show cause" why the contract should not be terminated for default within 10 days. AEC did not respond, and throughout the response period, AEC had only a handful of workers on the jobsite. The Navy terminated the contract for default.

The Armed Services Board of Contract Appeals held that the termination was invalid. ASBCA concluded that delays and modifications attributable to the government entitled AEC to an extension of time, which changed the contract completion date to May 16, 1991. ASBCA further ruled that the Navy had not presented any evidence that AEC could not complete contract performance by May 16, 1991.

The U.S. Court of Appeals for the Federal Circuit reversed ASBCA's decision. Danzig, v. AEC Corp., 224 F.3d 1333 (Fed. Cir. 2000) The court held that when the government justifiably issues a cure notice, the contractor has an obligation to take steps to demonstrate or give assurances that progress is being made toward a timely completion of the contract or to explain that the reasons for any prospective delay in completion of the contract are not the responsibility of the contractor. In this case, the issuance of a cure notice was justified under the circumstances, even if the circumstances did not, at that point, justify a termination for default. The court found that in response to the Navy's March 1991 cure notice, AEC failed to give the Navy adequate assurances that it could complete the contract on a timely basis or even that it could continue to make progress toward completion.

The court found that AEC's assertions of government-caused delay did not respond adequately to the Navy's request for assurances. AEC was not specific as to what changes had caused delay or how much delay it considered the government to have caused, and AEC did not represent that it could complete the contract within the additional time to which it believed it was entitled. Citing Restatement (Second) of Contracts §251 and Uniform Commercial Code §2-609, the court concluded that AEC's failure to respond adequately to the Navy's reasonable request for assurances of timely performance justified the Navy's termination of the contract for default.


If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form.


For more information about the issues covered in this report, please contact Paul Berning in our San Francisco office at 415-369-7229 or at pwberning@thelen.com or contact your Thelen attorney. For more information about Thelen's Construction and Government Contracts Department, click here.





©2001 Thelen Reid Brown Raysman & Steiner LLP

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© Thelen Reid Brown Raysman & Steiner LLP
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About Thelen ConstructionWebLinks Contact Us