|
Thelen Reid Brown Raysman & Steiner LLP
The
U.S. Court of Appeals for the Federal Circuit has handed
down two decisions clarifying when federal contractors may
recover Eichleay damages for unabsorbed home office
overhead.
The
decisions spell out the elements that contractors must prove
to qualify for Eichleay damages. And, they make clear that
mere disruption of workplans, inefficiency or re-sequencing
will not entitle the contractor to Eichleay damages.
Elements of Proof
A contractor
entered into a fixed-price contract with the Department
of Veterans Affairs to build a hospital addition in Ann
Arbor, Michigan. During the project, the VA issued more
than 400 change orders, causing multiple delays and increasing
the contract price by more than 5 percent. The VA granted
the contractor an additional 107 days of time to complete
the contract.
In
accepting the time extension, the contractor reserved its
right to seek additional impact and suspension costs, including
unabsorbed home office overhead under the Eichleay
formula. The contract was completed 260 days after the original
contract completion date and 153 days after the revised
completion date.
After completion,
the contractor presented its claims to the contracting officer.
The CO denied all of the claims, and the contractor appealed
to the Veterans Affairs Board of Contract Appeals. The contractor
claimed that it was entitled to a 260-day time extension
as well as field and home office overhead damages for most
of the delays.
VABCA
granted time extensions for the full 260 days but, based
on the contract’s Suspension of Work clause, determined
that the contractor was due only 65 days of field overhead
damages. VABCA also rejected the contractor’s claims
for Eichleay damages, concluding that the stipulation
between the parties had not relieved the contractor of the
burden of proving entitlement to Eichleay damages.
VABCA determined that the contractor had not shown that
it was on standby, a necessary element of an Eichleay
claim, and was thus ineligible to recover for unabsorbed
home office overhead.
The contractor
appealed, contending that a contractor is automatically
on standby any time there is a government-caused delay of
an uncertain duration that extends performance of the contract
and at the end of which the contractor can be required to
immediately resume work.
The
U.S. Court of Appeals for the Federal Circuit rejected the
contractor’s legal definition of standby and affirmed
VABCA’s determination that the contractor was not
on standby. Nevertheless, the court reversed VABCA’s
denial of the contractor’s claim for unabsorbed home
office overhead and remanded the case to VABCA for calculation
of such damages. P.J. Dick, Inc. v. Department of Veterans
Affairs, 324 F.3d 1364 (Fed. Cir. 2003).
In
its decision, the Federal Circuit enumerated the questions
a court should ask when evaluating a contractor’s
claim for Eichleay damages:
| 1. |
Was
there a government-caused delay that was not concurrent
with another delay caused by some other source? |
| |
|
| 2. |
Did
the contractor demonstrate that it incurred additional
overhead costs? |
| |
|
| 3. |
Did
the government CO issue a suspension or other order
expressly putting the contractor on standby? |
| |
|
| 4. |
If
not, can the contractor prove there was a substantial
delay of indefinite duration during which it could not
bill substantial amounts of work on the contract and
at the end of which it was required to be able to return
to work on the contract at full speed and immediately? |
| |
|
| 5. |
Can
the government show that it was not impractical for
the contractor to take on replacement work (i.e., a
new contract) and thereby mitigate its damages? |
| |
|
| 6. |
If
the government meets its burden of production as set
out in Question No. 5, can the contractor satisfy its
burden of persuasion that it was impractical for it
to obtain sufficient replacement work? |
The
court held: “Only where the above exacting requirements
can be satisfied will a contractor be entitled to Eichleay
damages.”
The
Federal Circuit took a particularly close look at the fourth
question in an effort to clarify what it called the “multi-faceted”
inquiry of standby. In the absence of an express order from
the CO putting the contractor on standby, the court said,
the contractor must prove standby by the following indirect
means:
| 1. |
The
contractor must show that the government delay was not
only substantial but was of indefinite duration. (For
example, when the government suspends all work on the
contract but tells the contractor that the work will
begin again on a certain date, the contractor cannot
be on standby.) |
| |
|
| 2. |
The
contractor must show that during that delay it was required
to be ready to resume full work immediately. (Thus,
when the government gives the contractor a reasonable
amount of time to remobilize its workforce once the
suspension is lifted, the contractor cannot be on standby.) |
| |
|
| 3. |
The
contractor must show effective suspension on much, if
not all, of the work on the contract. |
The
court thereby imposed a narrower definition of standby that
requires the contractor to show a suspension, either formal
or functional, of all or most of the work on the contract.
Applying this more stringent interpretation of the standby
requirement, the court rejected the contractor’s legal
argument.
Moreover,
the court agreed with the fact findings of VABCA: The contractor
continued to perform substantial amounts of work on the
contract -- nearly half what it planned -- during the alleged
periods of suspension. As a result, the court concluded
that the contractor was not on standby.
Despite
the court’s lengthy exposition on the ground rules
for an Eichleay damages claim and the court’s
detailed inquiry into the issue of standby, the Federal
Circuit ultimately decided in favor of the contractor on
an entirely different basis: the parties’ negotiated
“Stipulation on Quantum.”
The
court held: “The language of the stipulation establishes
a single condition precedent to [the contractor’s]
receipt of the enumerated damages [for field and home office
overhead]: entitlement to damages under the SOW [suspension
of work] clause.” The stipulation, the court determined,
“removed the need for [the contractor] to separately
prove entitlement to home office overhead damages”
under Eichleay.
No Claims for Lost Efficiency
The second
case involved a contractor that entered into a fixed-price
contract to improve and repair a building at an Army medical
center in Colorado. The work was to be accomplished in two
phases. Phase 1 dealt with the south half of the building;
Phase 2 dealt with the north half of the building. The work
on Phase 1 was to be completed within 190 days of the notice
to proceed from the government. It was understood by both
parties that the government would vacate that part of the
building under construction.
Following
notice to proceed, the government failed to vacate the southern
half of the building as agreed, causing substantial delays
in the contractor’s performance. Other problems included
defects in the government’s specifications, a large
number of change orders issued by the government and deficiencies
in the performance of the contractor and its subcontractors.
Six months
after the original completion date, the parties met and
agreed on a two-month extension of time for performance
of Phase 1. The contractor did not complete Phase 1 until
93 days after the extended completion date, and the government
eventually terminated for convenience the contractor’s
work on Phase 2.
Contractor
subsequently filed claims, including an Eichleay
claim for unabsorbed home office overhead. The Armed Services
Board of Contract Appeals allowed certain claims but denied
the contractor’s Eichleay claim based on
a Defense Contract Audit Agency report alleging that overhead
for the disputed period was “fully absorbed by the
basic contract, contract modifications, and other projects”
and “the contractor used both variable and fixed overhead
expenses in computing the average daily overhead rate.”
The contractor appealed.
The
U.S. Court of Appeals for the Federal Circuit rejected ASBCA’s
decision, ruling that ASBCA’s function was to determine
whether the contractor “had established its case for
Eichleay damages, not whether the auditor’s
‘finding’ that [the contractor] had not done
so was supported by the record.” Based on ASBCA’s
opinion, the court could not “determine whether it
properly rejected [the contractor’s] Eichleay
claim or determine how that question should be answered.”
On
remand, ASBCA once again rejected the contractor’s
Eichleay claim but, at the direction of the court,
broadened the evidentiary basis of its decision, directly
addressing the contractor’s entitlement to Eichleay
damages. ASBCA determined that the contractor had failed
to show standby because it had not shown that “performance
of the work was suspended or significantly interrupted during
the period” in dispute. The contractor again appealed.
The
U.S. Court of Appeals for the Federal Circuit affirmed ASBCA’s
decision. Charles G. Williams Construction, Inc. v.
Thomas E. White, Secretary of the Army, 326 F.3d 1376
(Fed. Cir. 2003).
In
its first opinion, the court had reiterated from prior decisions
that one of the “two prerequisites to application
of the Eichleay formula to recover unabsorbed overhead
[caused by government delay]” is that the contractor
be on standby. Charles G. Williams Construction, Inc.
v. Thomas E. White, Secretary of the Army, 271 F.3d
1055 (Fed. Cir. 2001). “The proper standby test,”
the court continued, ”focuses on the delay or suspension
of contract performance for an uncertain duration, during
which a contractor is required to remain ready to perform….
If both of these requirements are satisfied, the contractor
has shown that it had unabsorbed general overhead for which
it is entitled to Eichleay damages.”
In its second
opinion, the court found that the contractor had failed
to provide evidence that on any particular day it was unable
to do any work at all on the contract while obliged to be
ready to resume full work immediately. Nor was there any
evidence that the government directed the contractor to
remain idle and on call.
The
court also called attention to the contractor’s apparent
misunderstanding of the concept of “standby”
as it relates to an Eichleay claim. In its brief,
the contractor argued that a contractor would be entitled
to Eichleay damages when the government significantly
interfered with efficient performance of the contract. Similarly,
in oral argument the contractor answered affirmatively when
asked whether a contractor is entitled to Eichleay
damages if, as a result of government delay, the contract
cannot be performed as efficiently or effectively as it
was understood it should have been performed.
The
court responded that such a showing would not be sufficient
to establish entitlement to Eichleay damages. That
is because “such damages are utilized to compensate
a contractor for its indirect costs that cannot be allocated
to a particular contract for the period during which the
government has made contractual performance impossible,
while requiring the contractor to remain available to resume
performance on short notice.”
The
court added: “As long as the contractor is able to
continue performing the contract, although not in the same
way or as efficiently or effectively as it had anticipated
it could do so, it can allocate a portion of its indirect
costs to that contract. There is accordingly no occasion
in that situation to resort to ‘recovery under the
Eichleay formula,’ which is ‘an extraordinary
remedy.’ ”
If you would like to receive legal reports and
updates more quickly, by e-mail, click
here and fill out the mailing list form.
For more information about the issues covered in this report, please contact Paul Berning in our San Francisco office at 415-369-7229 or at pwberning@thelen.com or contact your Thelen attorney. For more information about Thelen's Construction and Government Contracts Department, click here.

©2003 Thelen Reid Brown Raysman & Steiner LLP
|