 |
Thelen Reid Brown Raysman & Steiner LLP
New
York's highest court, the New York Court of Appeals, created
a new common law doctrine that may allow, among other things,
a party to certain complex, long-term construction contracts
to demand assurance of future performance from another party
when reasonable grounds exist to believe that the other
party will not perform its obligation under the contract.
If the party from whom adequate assurance is demanded does
not provide such assurance within a reasonable time, that
party is deemed to have repudiated the contract, and the
non-breaching party may take reasonable actions as though
repudiation had occurred.
In New York, before the Court of Appeals' decision in Norcon
Power Partners, L.P. v. Niagara Mohawk Power Corp. [92
N.Y.2d 458, 682 N.Y.S.2d 664, 705 N.E.2d 656 (1998)], the
doctrine of adequate assurance of future performance essentially
was a Uniform Commercial Code doctrine, applicable only
to contracts for the sale of goods. In the vast majority
of states, the doctrine of adequate assurance of future
performance remains limited to the Uniform Commercial Code.
The New York Court of Appeals is the highest and most influential
court in the United States to have created a common law
doctrine of adequate assurance of future performance, applicable
outside of the sale of goods context, and its decision may
be followed by courts in other states.
The Facts. The Norcon case was not a
construction case. In Norcon, Norcon was an
independent producer of electricity. Niagara Mohawk
was a provider of electricity to public utilities.
Norcon and Niagara Mohawk entered into a contract under
which Niagara Mohawk agreed to purchase electricity from
Norcon for 25 years. The contract contained three
different pricing periods.
In the first period, Niagara Mohawk paid Norcon a flat rate
per kilowatt-hour for electricity. In the second period,
Niagara Mohawk paid Norcon according to an "avoided cost"
rate that was based upon the cost that Niagara Mohawk would
have incurred to either generate electricity itself or purchase
it from other sources. The second pricing period also
contained a "floor" price, namely, a minimum price that
Niagara Mohawk would have to pay Norcon for electricity
for the second period even if Niagara Mohawk did not purchase
an amount of electricity for the period that equaled the
floor price at the avoided cost rate. An "adjustment
account," however, kept track of any difference between
the payment actually made by Niagara Mohawk during the second
period and what Niagara Mohawk's payment to Norcon would
have been if based solely on the avoided cost rate.
That is, if Niagara Mohawk was required to pay the floor
price, the adjustment account would keep track of the difference
between the floor price and what Niagara Mohawk would have
paid to Norcon if its payment was based solely on the avoided
cost rate.
Lastly, in the third pricing period, Niagara Mohawk paid
Norcon according to the avoided cost rate adjusted to account
for any balance existing in the adjustment account.
For example, if the payment actually made by Niagara Mohawk
in the second period exceeded what the payment would have
been if based solely on the avoided cost rate, the amount
paid by Niagara Mohawk in the third period would be reduced
to reflect the difference. Any amount left over in
the adjustment account in favor of Niagara Mohawk at the
end of the third period would have to be paid to Niagara
Mohawk within 30 days of the end of the period.
Within the first few years in the performance of the contract,
Niagara Mohawk estimated that it would accrue over $610
million in the adjustment account by the end of the second
pricing period. Concerned that Norcon would neither
be able to credit this amount in the third pricing period
nor repay it at the end of the third period, Niagara Mohawk
wrote Norcon demanding that "Norcon provide adequate assurance
to Niagara Mohawk that Norcon will duly perform all of its
repayment obligations." In response, Norcon promptly
sued Niagara Mohawk in federal court, asserting that Niagara
Mohawk had no contractual right under New York state law
to demand adequate assurance of Norcon's future payment
performance under the contract. Niagara Mohawk countered
that it could properly invoke such a right.
The United States District Court, Southern District of New
York, found in favor of Norcon, reasoning that New York
law only recognizes the doctrine of demand for adequate
assurance of future performance in two limited circumstances:
(1) when the obligor becomes insolvent or (2) when
the sale of goods under UCC 2-609 is involved. Since
neither circumstance was involved in the case, the District
Court was constrained to rule in favor of Norcon.
Niagara Mohawk appealed the District Court's decision to
the Second Circuit Court of Appeals, which preliminarily
agreed with the District Court but refrained from making
a final decision until it could ask New York State's highest
court, the New York Court of Appeals, if New York law only
recognizes the doctrine of demand for adequate assurance
of future performance in the two limited circumstances mentioned
above.
The Holding. The New York Court of Appeals
took up the Second Circuit's question. It found New
York until then had refrained from expanding the right to
demand adequate assurance of future performance beyond the
Uniform Commercial Code but declared that it was time for
a "modern pronouncement" governing the kind of contract
and dispute between Norcon and Niagara Mohawk. Accordingly,
the Court of Appeals created a new common law analogue to
the statutory doctrine of demand for adequate assurance
of future performance in UCC 2-609 that would apply outside
of the sale of goods context and held that the new doctrine
should apply to the type of long-term commercial contract
entered into by Norcon and Niagara Mohawk.
The doctrine of demand for adequate assurance of future
performance as embodied in UCC 2-609 allows a party to a
contract for the sale of goods to demand assurance of future
performance from another party when reasonable grounds for
insecurity exist. If the other party does not provide
adequate assurance within a reasonable time, that party
is deemed to have breached the contract and the non-breaching
party may act accordingly. UCC 2-609 recognizes that
"the essential purpose of a contract between commercial
[parties] is actual performance... and that a continuing
sense of reliance and security that the promised performance
will be forthcoming when due, is an important feature of
the bargain." (Official Comment 1 to UCC 2-609).
In reaching its decision to create a new common law doctrine
of demand for adequate assurance of future
performance, the Court of Appeals seemed most persuaded
by the fact that the policies behind UCC 2-609 are not unique
to contracts for the sale of goods. Whether a contract
is for the sale of goods or for the performance of services,
"the parties to a contract look to actual performance...
and a continuing sense of reliance and security that the
promised performance will be forthcoming when due, is an
important feature of the bargain." (Restatement [Second]
of Contracts § 251, comment a, quoting comment 1 to UCC
2-609). Accordingly, the Court decided to create a
common law analogue to UCC 2-609 because it puts commercial
parties in such disputes "at relatively arms length equilibrium
in terms of reliability and uniformity of governing legal
rubrics."
Applicability to the Construction Industry. The
new common law doctrine of demand for adequate assurance
of future performance, however, most likely will not apply
to all construction contracts. The Court of Appeals
rejected a "wholesale" application of the adequate assurance
doctrine to all contract disputes. Instead, the Court
carefully focused its ruling on the case before it, stating
that the new common law doctrine "should apply to the type
of long-term commercial contract between corporate entities
entered into by Norcon and Niagara Mohawk here, which is
complex and not reasonably susceptible of all security features
being anticipated, bargained for and incorporated in the
original contract."
Only time will tell to what type, if any, of construction
contract the new common law doctrine created by the Court
of Appeals in Norcon will apply. Clearly, the
greater the complexity, the longer the term, and the less
susceptible of incorporated security features the construction
contract, the more likely that the new adequate assurance
doctrine will apply. In sum, the New York Court of
Appeals' decision in Norcon is a significant development
in the world of construction law, for it may portend a new
day in which parties to certain long-term construction contracts
have the right to demand adequate assurance of future performance
when they have reasonable grounds to believe another party
may breach the agreement.
If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form.
For more information about the issues covered in this report, please contact Richard P. Dyer in our New York office at 212-895-2117 or at rpdyer@thelen.com or contact your Thelen attorney. For more information about Thelen's Construction and Government Contracts Department, click here.

©1998 Thelen Reid Brown Raysman & Steiner LLP
|