|
You could be managing construction of a high-rise project
in New York City, a power plant in India or a paper mill
in Brazil, and on any of those projects your legal disputes
could be subject to resolution under New York law. While
it is common to provide that domestic construction project
disputes are to be governed by the law of the place where
the project is located, often on large, international projects
and on project-financed jobs, the contracts are subject
to the law of New York, where the financing parties and
their legal counsel often are located.
Decisions
from New York courts on construction-industry-related topics
will be summarized here periodically. Some of the decisions
will be from appellate courts, which establish new law or
clarify existing law. Others will be from trial courts,
whose decisions on construction disputes generally are not
reported to the industry or public. Nevertheless, these
trial court decisions reflect how common construction contract
disputes are likely to be resolved in similar cases.
Many
of the decisions are accessible in full online, and links
are provided to them. For those not available online, the
full text can be obtained in hard copy by e-mailing Richard
P. Dyer at rpdyer@thelen.com.
By
Richard P. Dyer Thelen Reid Brown Raysman & Steiner LLP
On
the heals of an appellate court's decision permitting commercial
and retail tenants to recover lost profits from the owners
and managers of a nearby building that partially collapsed
and caused street closings, the same court now has held
that a law firm and others similarly situated cannot sue
for "inconvenience costs" arising from a hoist
tower collapse. In the earlier decision, the court held
that local merchants had "a right to carry on their
businesses free from the wrongful conduct of nearby property
owners" but "were subjected to the consequences
of defendants' failure to maintain their building in a reasonably
safe manner despite obvious notice of the overt risks and
potentially deleterious consequences of their misconduct.
" 5th Avenue Chocolatiere, Ltd. v. 540 Acquisition
Co., 2000 N. Y. App. Div. LEXIS 7573 (1st Dept. July
6, 2000) and the companion case of 532 Madison Avenue
Gourmet Foods, Inc. v. Finlandia Center, Inc., 2000
N.Y. App. Div. LEXIS 7571 (1st Dept. July 6, 2000). A summary
of the earlier cases is available at:
www.
constructionweblinks. com/Resources/
Industry_Reports__ Newsletters/Aug_7_2000/
economic_loss_rule.htm.
The
recent case arose out of the collapse of the exterior hoist
tower utilized in construction of Two Times Square, which
resulted in death, property damage and street closings.
The purported class sought damages not limited to lost profits
but also sought to recover all ancillary inconvenience costs,
which were common to the entire community and thus not special
or peculiar. The court held that such damages common to
the community are not recoverable in a nuisance action.
More importantly, the court held that the economic damages
suffered "are too attenuated to be reasonably foreseeable
consequences of the collapse of the elevator tower"
and thus are insufficient to support a negligence action.
Finally, the court noted, in distinguishing its earlier
decision, that the "purported negligence of defendants.
. . was not as egregious as that alleged against the defendants"
in 5th Ave. Chocolatiere and 532 Madison Ave., "where
the defendants allegedly punched more than 90 window holes
in the wall of a building which they knew or should have
known to be unstable and designed to be windowless."
Goldberg
Weprin & Ustin LLP v. Tishman Construction Corp.,
App. Div. 1st Dept.; September 14, 2000.
Extra Work Claims Dismissed Because Contractor Did Not
Request Approval of Change Orders; Delay Claims Dismissed
Because Coordination Delays Were Contemplated
A
contractor on a multi-prime school project sought recovery
of additional costs for a variety of causes, including differing
site conditions, unreasonable and untimely changes to the
work, late responses to RFIs, denial of access, preferential
access to other contractors, and manipulation of schedules.
Defendant
moved for summary judgment, which was opposed by the contractor
on the grounds of factual issues concerning the defendant's
breach of fundamental obligations under the contract by
providing defective plans and delaying the project. The
court determined that plaintiff was unable to point to any
specific provision of the contract that was breached and
found that the damages for which plaintiff sued had not
been the subject of change order requests although plaintiff
had used the change order procedure for other items and
understood it. The court held that plaintiff was barred
by the contract from recovery as to these damages. Plaintiff's
claims relating to delays to the work failed in view of
a no damages for delay clause.
The
court further found that contract provisions that referred
to the planned award of 14 separate contracts alerted plaintiff
to the possibility of delays caused by coordination problems
and, thus, had been contemplated by the parties. The court
also found that "mere bad administration on the part
of the owner does not rise to the level of willful, malicious
or grossly negligent conduct" so as to constitute an
exception to the no damages for delay clause.
Tougher
Industries v. Board of Education of the City of Rochester,
Supreme Court, Monroe County; Judge Stander; June 2000.
Anti-Assignment Clause Does Not Bar Assignment Unless
Clear Language Declares It Void or Invalid
Declaratory
judgment was sought regarding the right of a beneficiary
of a settlement agreement to sell the entitlement to receive
future payments, given anti-assignment language in the agreement.
A clause prohibited assignment, but the agreement elsewhere
referred to assigns and successors in interest. The court
ruled that the assignment was permissible since the agreement
did not contain an express statement that an assignment
would be void or invalid; a mere prohibition would give
rise to a claim for damages but not invalidate the transfer.
"Only language specifically addressing the consequences
of an assignment and declaring it to be 'void' or 'invalid'
or 'not binding' will render the assignment unenforceable.
" In addition, the court identified other ambiguities
in the agreement that suggested contemplation of assignment
of the agreement.
C.
U. Annuity Service Corp. v. Young; Supreme Court, New
York County; Judge Cahn; June 19, 2000.
Public Owner's Attempt to Require Notice of Claim to
Recover Contract Balance Rejected
Plaintiff
asbestos abatement contractor sued the New York City Housing
Authority for the balance of the contract price for removal
of asbestos and re-insulation. The Housing Authority asserted
that it had the right to reduce the contract price because
the amount of asbestos to be removed and replaced was less
than the Housing Authority's estimate, which was included
in the bid documents. The court rejected the Housing Authority's
contention that the changes clause empowered it to reduce
the contract price. The court also rejected the Housing
Authority's procedural defense, finding that a notice of
claim was not a prerequisite to maintaining an action for
a contract balance because the contract's notice of claim
clause applied only to claims for additional compensation.
In rejecting the Housing Authority's substantive and procedural
defenses, the court concluded they were "based on serious
misreadings of the contractual provisions upon which they
were based."
J&R
Contracting and Environmental Consulting v. New York City
Housing Authority; Civil Court, New York County; Judge
Samuels; May 30, 2000.
Designation of Contractor's Representative as Final Arbiter
in a Subcontract Is Upheld
A
dispute resolution provision in a subcontract provided that
the parties authorized the contractor's representative to
decide all questions of any nature arising out of the subcontract,
and his decision was to be final and binding. His decision
was subject to review only on the grounds that it was arbitrary,
capricious or grossly erroneous so as to evidence bad faith.
The provision further provided that use of the procedures
was a "precondition" to any lawsuit. The subcontractor
challenged the provision on the grounds that it was not
a clear and unequivocal ADR agreement that must be followed
before seeking relief in court. The court disagreed, citing
New York's public policy in favor of arbitration and ADR
and the clear language of the subcontract, which the subcontractor
accepted "with its business eyes open."
Fergusson
Electric Co. v. Kendal at Ithaca, Inc., 711 N.Y.S.2d
246 (3rd Dept., March 27, 2000).
Claim Barred by Lack of Verification
The
contractor on a public contract for capping a landfill sought
an equitable adjustment because of the rejection of and
subsequent modification of the site grading plans. The contract
included typical public contract notice-of-claim and record-keeping
requirements. The contractor was to file a written notice
of claim within 30 days of an order to perform extra work
or the commencement of such work and, within the same time
period, "a verified, detailed statement, with documentary
evidence, of the items and the basis of his claim. "The
contract further specifically precluded commencing an action
on a claim unless there was strict compliance with the notice
provisions for the claim. The contractor provided a timely
written notice of its claim. However, the court found that
the notice was not "properly verified in any manner
nor sufficiently supported by documentary evidence."
Because strict compliance was required, the complaint was
dismissed on grounds that the claim was patently insufficient.
Tug
Hill Construction, Inc. v. County of Broome, 704 N.Y.S.2d
391 (3rd Dept., March 23, 2000).
Bid Is Binding for 120 Days; Contract Formed When Bid
Accepted
The
City of New York defaulted a contractor before work began
and called on the contractor's surety to arrange for performance.
The surety sought and obtained competitive bids and issued
a notice of award to the low bidder. The bidder withdrew
its bid and refused to enter into a completion contract.
With only two options available to the surety, award to
the second low bidder or settling with the city, surety
chose to settle and pay the city $150,000. The surety then
sued the low bidder for funds it expended to settle with
the city. The court granted summary judgment to the surety
on the issue of liability, finding that under the terms
of the bid documents, any bid submitted was irrevocable
for 120 days. When the surety accepted defendant's bid within
that time period, a binding contract was formed.
Carolina
Casualty Ins v. ADC Contracting and Construction; Supreme
Court, New York County, Judge Cahn, September 22, 2000.
Subcontractor Delayed by Contractor's Inept Administration
Gets No Relief
A
subcontractor on a public works project sought damages due
to delays and extra work caused by the conduct of the prime
contractor. The court enforced the subcontract's no-damage-for-delay
provision, finding that the record did not establish that
the prime contractor's actions rose to the level of one
of the four recognized exceptions: (1) the product of willful,
malicious or grossly negligent conduct; (2) uncontemplated
delays; (3) so unreasonable as to constitute abandonment
of the subcontract; or (4) the result of a breach of a fundamental
obligation of the subcontract. While the record did reflect
delays caused by "inept administration" by the
prime contractor, such conduct was covered by the subcontract's
exculpatory provisions. This case follows previous decisions
holding that mal-administration of construction contracts
by public bodies does not fall within the noted exceptions
to a no damage for delay clause.
S. N. Tannor, Inc. v. A.F.C. Enterprises, Inc.; App. Div. 1st Dept.; October 19, 2000
If you would like to receive legal reports and updates
more quickly, by e-mail, click
here and fill out the mailing list form.
For more information about the issues covered in this report, please contact Richard P. Dyer in our New York office at 212-895-2117 or at rpdyer@thelen.com or contact your Thelen attorney. For more information about Thelen's Construction and Government Contracts Department, click here.

©2000 Thelen Reid Brown Raysman & Steiner LLP
|