Construction Web guide: infrastructure, buildings, engineering, architectureThelen Reid Brown Raysman & Steiner
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About Thelen ConstructionWebLinks Contact Us

Public-Private Partnerships
Private Financing of Infrastructure in California: Overview of PPP Opportunities and Challenges

'Material Effect'
U.S. Supreme Court Clarifies Proof Needed to Impose False Claims Act Liability on Subcontractors

Got Early Completion
Owner’s Oral Promise to Pay Subcontractor Enforced by Massachusetts Court

Block Claims of Waiver
When Loans Go Bad, Pre-Workout Agreements Allow Lenders to Protect Their Rights While Negotiating

Bankruptcy Code Is No Bar
Bankrupt Sub’s Claim Against General Contractor Is a Non-Core Proceeding and Must Be Arbitrated, U.S. Court Holds

Saves Time
Prequalification in Government Construction Contracts: How It Works, How Disputes Are Resolved

Fabrication, Design Cases
U.S. Court Permits Quantum Meruit Claims for Work Not Controlled by Contract

No Own Work Exclusion
Florida, South Carolina Supreme Courts Hold that Contractors’ CGL Policies Cover Damages Arising from Subs’ Defective Work

Previous Issues

Construction Industry News

South Dakota Approves Use of Total Cost Method of Pricing Damages


July 16, 2001


Back to Industry Newsletters
 

Thelen Reid Brown Raysman & Steiner LLP

Defendant was awarded a subcontract to perform concrete work on plaintiff's home. Defendant was to complete the job "per specifications." During the work, defendant claimed to have encountered difficulties (i.e., inadequate access to the site, improper excavation and numerous changes to the blueprints) for which he was not reimbursed. After defendant had worked for nearly a year on the project, the general contractor ordered defendant to cease activity and remove his equipment from the jobsite.

Defendant recorded a mechanic's lien against plaintiff's property. In response, plaintiff filed a lawsuit against defendant alleging damages for overpayments, extra costs to complete defendant's work by another contractor and extra costs to pay defendant's supplier to release a lien on plaintiff's property. Defendant counterclaimed, seeking compensatory and punitive damages for breach of contract and for breach of the implied covenant of good faith and fair dealing.

The Supreme Court affirmed the trial court's ruling dismissing the punitive damage claim on grounds that state law precluded an independent tort action for breach of the implied covenant of good faith and fair dealing. Punitive damages cannot be recovered for breach of contract; only contract damages. McKie v. Huntley, 620 N.W.2d 599 (S.D. 2000).

The Supreme Court, however, reversed the trial court's dismissal of defendant's damage calculations on the basis that such damages were speculative. Defendant had used a total cost approach in calculating damages. The Supreme Court found that once liability and causation were established by a preponderance of the evidence, the total cost method of calculating damages "should be applied where the nature of the particular loss has made it impossible or highly impracticable to determine damages with a reasonable degree of accuracy and where the loss is substantiated by reliable evidence."

The court further held that there are cases when "the total cost method is the best and only means of quantifying the impact of changes on a contractor." The court concluded that "based on the nature of this construction contract dispute, with its many reciprocal allegations of delay and nonperformance," the total cost approach could be a reasonable approach to calculating damages.


If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form.


For more information about the issues covered in this report, please contact Paul Berning in our San Francisco office at 415-369-7229 or at pwberning@thelen.com or contact your Thelen attorney. For more information about Thelen's Construction and Government Contracts Department, click here.





©2001 Thelen Reid Brown Raysman & Steiner LLP

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© Thelen Reid Brown Raysman & Steiner LLP
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About Thelen ConstructionWebLinks Contact Us