Construction Web guide: infrastructure, buildings, engineering, architectureThelen Reid Brown Raysman & Steiner
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About Thelen ConstructionWebLinks Contact Us

Public-Private Partnerships
Private Financing of Infrastructure in California: Overview of PPP Opportunities and Challenges

'Material Effect'
U.S. Supreme Court Clarifies Proof Needed to Impose False Claims Act Liability on Subcontractors

Got Early Completion
Owner’s Oral Promise to Pay Subcontractor Enforced by Massachusetts Court

Block Claims of Waiver
When Loans Go Bad, Pre-Workout Agreements Allow Lenders to Protect Their Rights While Negotiating

Bankruptcy Code Is No Bar
Bankrupt Sub’s Claim Against General Contractor Is a Non-Core Proceeding and Must Be Arbitrated, U.S. Court Holds

Saves Time
Prequalification in Government Construction Contracts: How It Works, How Disputes Are Resolved

Fabrication, Design Cases
U.S. Court Permits Quantum Meruit Claims for Work Not Controlled by Contract

No Own Work Exclusion
Florida, South Carolina Supreme Courts Hold that Contractors’ CGL Policies Cover Damages Arising from Subs’ Defective Work

Previous Issues

Construction Industry News

Nebraska Contractor Denied Relief for Breach of Contract After Pursuing Mechanic's Lien Remedy in Another Suit


Back to Industry Newsletters
 

(A revised version of this article will appear in The Construction Lawyer, Volume 21, No. 2, April 2001, published by the American Bar Association's Forum on the Construction Industry.)


March 12, 2001


By John W. Ralls
Thelen Reid Brown Raysman & Steiner LLP

A contractor and an owner entered into a lump sum oral contract for the erection of a new building. After a relatively small amount of progress had been made, a dispute arose between the owner and the contractor concerning the pricing of certain changes and extra work. The owner stopped making payments and terminated the contractor. The contractor filed a construction lien.

In an action on the lien, the contractor had sought to foreclose the lien but did not sue for breach of contract. See Tilt-Up Concrete, Inc. v. Star City/Federal, 255 Neb. 138, 582 N.W.2d 604 (1998) ("Tilt-Up I"). In that action, the contractor argued it was entitled to a lien for the unpaid contract amount, less savings for unperformed work, based on Nebraska's lien statute. Nebraska's lien law provides that "the lien of a prime contractor is for the unpaid part of his or her contract price...." Nebraska Revised Statutes §52-136 (1) (a). "[C]ontract price" is defined as "the amount agreed upon by the contracting parties for performing services and furnishing materials covered by the contract, increased or diminished by the price of change orders or extras, amounts attributable to altered specifications, or breach of contract...." Id. §52-127 (2).

In the lien foreclosure action, the trial court determined that the contractor had a valid lien in the amount of $852,243, the full amount of the contractor's breach of contract damages, including lost profit on unperformed work. In Tilt-Up I, the Nebraska Supreme Court held that when a prime contractor has not substantially performed a contract, the contractor is entitled to a construction lien only for the reasonable value of the labor performed and the materials furnished. The Nebraska Supreme Court reduced the amount of the contractor's lien to $235,418. Tilt-Up I, 255 Neb. at 151-156, 582 N.W.2d at 613-615.

The contractor then filed another action seeking damages for breach of contract. The owner demurred on the ground that the action was barred by the four-year statute of limitations. The trial court sustained the demurrer, and the contractor appealed. The Nebraska Supreme Court affirmed. Tilt-Up Concrete, Inc. v. Star City/Federal, Inc., 261 Neb. 64, 2001 Neb. LEXIS 13 (2001)

On the face of the petition, the contractor's breach of contract claim was barred by the statute. The contractor claimed that during the pendancy of the lien foreclosure action, it was precluded from bringing a breach of contract action, and therefore, the statute of limitations was equitably tolled. The court rejected this argument.

The court found that as a general rule, in Nebraska and throughout the United States, mechanic's lien foreclosure and breach of contract damages may be sought at the same time. "[T]he NCLA [Nebraska Contractors' Lien Act] does not take away a construction lienholder's common law right to sue for breach of contract. The only limitation is that any amount recovered for breach of contract damages would be credited to satisfy the construction lien when necessary to prevent double recovery."

The contractor also argued it was precluded from bringing its breach of contract action by a supersedeas bond filed by the owner in connection with the appeal in Tilt-Up I, which "secured the full amount of the lien and breach of contract damages...." The court rejected this argument on the ground that a supersedeas bond serves only to suspend further proceedings on the judgment or decree appealed from. "[A] supersedeas bond furnished in one cause will not operate to suspend or prevent the enforcement of a judgment or decree rendered in another and different action."

Finally, the contractor argued that it was barred by the mortgage foreclosure statutes, Nebraska Revised Statute §§25-2137 through 25-2155, from seeking lien foreclosure and breach of contract damages at the same time. Under Nebraska's mortgage foreclosure statutes, after a mortgage foreclosure petition is filed, "no proceedings whatever shall be had at law for the recovery of the debt secured by the mortgage" while the action is pending. The contractor claimed that its action was similarly limited because Nebraska's construction lien law provides that "foreclosure [of a construction lien] may be by any method available for foreclosure of security interests in real estate...." The court rejected this argument on the ground that the Nebraska lien law does not limit the foreclosure proceeding to the mortgage foreclosure statute "but instead provides that the district court may utilize any method available for foreclosure, including but not limited to the mortgage foreclosure statutes."


If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form.


For more information about the issues covered in this report, please contact John Ralls in our San Francisco office at 415-369-7210 or at jralls@thelen.com or contact your Thelen attorney. For more information about Thelen's Construction and Government Contracts Department, click here.





©2001 Thelen Reid Brown Raysman & Steiner LLP

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© Thelen Reid Brown Raysman & Steiner LLP
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About Thelen ConstructionWebLinks Contact Us