Construction Web guide: infrastructure, buildings, engineering, architectureHowrey
Web directory of federal, state, local governments; courts; legislatures; Congress; trade groups; businesses; colleges; libraries; publications; international agencies affecting construction, engineering, architecture, infrastructure Web directory of resources on licensing, registration, building codes, new projects, bidding, financing, environment, specifications, e-commerce, laws, regulations, insurance, bonds, jobs, safety, best practices, engineering, architecture, training Web guide to dictionaries; encyclopedias; reference materials; business and international travel resources; people finders; telephone numbers; Web addresses; postal codes; currency, metric converters; time zones; calendars; travel; news
More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure
Site Search Site Map Registration About Howrey ConstructionWebLinks Contact Us

AIA Form
Declaration of Default Not Required to Trigger Surety’s Liability on Performance Bond, Court Holds

AIA, EJCDC, Consensus
Key Construction Insurance Issues – How 3 Form Contracts Address Them

Unless Collusion
Insurer Bound by Results of Insured’s Trial or Finding that Settlement Was Reasonable, Washington Supreme Court Holds

For Arbitrator to Decide
Statute of Limitations Is No Bar to Compelling Arbitration, California Supreme Court Holds

Courts Intervene
Arbitration Decisions: Finality May Not Always Be Best

Contract So Provides
Court Distinguishes Duty to Defend from Duty to Indemnify, Requires Non-Negligent Supplier to Pay for Defense

'Deplorable' and 'Irrational'
Government Acted in Bad Faith in Default Termination; Court Awards $17 Million in Damages to Contractor

Unexpected Interpretations
Standard Form Contracts – Choice of Law Can Change Everything

Previous Issues

Construction Industry News

Owner's Accord and Satisfaction Defense Fails When the Change Order Proposal Assumed Constant Work Conditions and the Conditions Varied


November 22, 2004


(A revised version of this article appears in The Construction Lawyer, Volume 24, No. 4, Fall 2004, published by the American Bar Association's Forum on the Construction Industry.)



By John W. Ralls
Howrey LLP

A general contractor was hired to remove and replace the roof of a Treasury Department building. The general contractor subcontracted portions of the work. When the subcontractor found an unexpected roof deflection problem on the south side of Wing D, it submitted a cost proposal to the contractor that: (1) sought $131,033 for extra work and (2) explained that it was assuming the remaining roof conditions for the rest of project would be similar to those on the south side of Wing D.

The general contractor sent the owner a letter, including the subcontractor's cost proposal. After adding its own expected costs, the general contractor requested a change order for $174,242 and a time extension of 42 days.

The contract was modified as proposed. The modification specifically stated that the changes were made pursuant to the contractor's proposal, which incorporated the subcontractor's cost proposal. The modification further stated that it was a "complete equitable adjustment" and provided the following release language: "The contractor hereby releases the [owner] from any and all liability under this contract for further equitable adjustment due to this modification."

After continuing work, the subcontractor found that the remaining roof conditions were different than those on the south side of Wing D. The subcontractor sought another equitable adjustment based on its assumption that the roof conditions would be similar to those on the south side of Wing D. In response, the contractor submitted another change order request to the owner. This time the owner denied the request. The general contractor appealed to the General Services Administration Board of Contract Appeals on behalf of the subcontractor, seeking a second equitable adjustment.

The owner moved for summary relief, arguing that the claim for an equitable adjustment was barred because when the parties modified the contract, they also had reached an accord and satisfaction. The owner argued that the release language in the modification barred the contractor and subcontractor from seeking additional compensation arising from roof deflections.

In response, the general contractor argued that "its proposal incorporated [the subcontractor's] proposal, which specifically qualified the estimate, noting that it was predicated on the assumption that conditions elsewhere on the roof would be comparable to those on the south side of wing D." Thus, the general contractor argued that it never agreed to release its right to further compensation if the conditions were worse on other parts of the roof.

The BCA denied the owner's motion for summary relief. Corning Construction Corp., 03-2 BCA ¶32,367 (GSA 2003). The BCA explained that generally "when a modification does not contain any reservation of claims, the modification constitutes an accord and satisfaction as to the subject matter of the modification and the contractor cannot later narrow the scope of the modification.... The essential elements of an accord and satisfaction are competent parties, proper subject matter, consideration, and a meeting of the minds."

The BCA found that a genuine issue of material fact existed as to whether there was a meeting of the minds (i.e., whether the general contractor actually intended to release its right to seek an equitable adjustment on all future claims). The BCA based its decision on the affidavit submitted by the general contractor's president stating that the general contractor never intended to release any claims based on conditions different from those on the south side of Wing D and from the subcontractor's assumption in its proposal that the remaining roof conditions would be the same as those on the south side of Wing D.

The BCA later granted the contractor's appeal as to entitlement, rejecting the owner's accord and satisfaction defense, and denied the owner's motion for reconsideration. 2004-1 BCA ¶¶32,402, 32,508. The parties then settled, with the contractor receiving a time extension, equitable adjustment, interest and attorney fees. 2004 GSBCA Lexis 63.


If you would like to receive legal reports and updates more quickly, by e-mail, click here and fill out the mailing list form. If you would like to subscribe to our RSS feeds or learn more about RSS, click here.


For more information about the issues covered in this report, please contact John Ralls in our San Francisco office at 415-848-3362 or at rallsj@howrey.com or contact your Howrey attorney. For more information about Howrey's Construction Practice Group, click here.



Send This Report to a Colleague

Tools to Share, Organize, Comment on Information


©2004 Howrey LLP

More than 500 online news and legal reports on construction law, including claims, payment remedies, damages, government contracting, insurance, building codes, licensing, technology, arbitration, engineering, architecture, infrastructure

© Howrey LLP
All rights reserved.
Legal notices, and terms and conditions.

Site Search Site Map Registration About Howrey ConstructionWebLinks Contact Us