|
You could be managing construction of a high-rise project
in New York City, a power plant in India or a paper mill in
Brazil, and on any of those projects your legal disputes could
be subject to resolution under New York law. While it is common
to provide that domestic construction project disputes are
to be governed by the law of the place where the project is
located, often on large, international projects and on project-financed
jobs, the contracts are subject to the law of New York, where
the financing parties and their legal counsel often are located.
Decisions
from New York courts on construction-industry-related topics
will be summarized here periodically. Some of the decisions
will be from appellate courts, which establish new law or
clarify existing law. Others will be from trial courts,
whose decisions on construction disputes generally are not
reported to the industry or public. Nevertheless, these
trial court decisions reflect how common construction contract
disputes are likely to be resolved in similar cases.
Many
of the decisions are accessible in full online, and links
are provided to them. For those not available online, the
full text can be obtained in hard copy by e-mailing Richard
P. Dyer at rpdyer@thelen.com.
By
Richard P. Dyer Thelen Reid Brown Raysman & Steiner LLP
The
electrical prime contractor on a multi-prime project sued
New York City and a public agency for failure to default
the prime general construction contractor long before that
party withdrew from the project. In a summary judgment motion,
defendants argued that a "no damages for delay"
clause barred the claim. The court found that the defendants
attempted to address the general contractor's failings and
thus there was no evidence of intentional or reckless wrongdoing.
The court further held that the delay was not unreasonable
nor of a type not contemplated by the underlying contract,
as other contractor delays were referenced in the contract.
The court also found that the claim was barred because the
plaintiff's failed to comply with the unusual notice and
filing provisions of the contract -- a written notice of
claim and commencement of an action within 60 days
afterward. Here, plaintiff filed the action and served a
notice of claim after the filing. Sound Electric
Corp. v. City of New York; Supreme Court, New York County;
Judge Stallman; June 2, 2000.
Dispute Board Decisions Get Deference Upon Review
The
contractor sought review of a Contract Dispute Resolution
Board determination in favor of the City of New York. Contractor
sought to overturn the board's determination that the contract
at issue included the cost of protecting certain cable television
lines. The court rejected the contractor's claim, holding
that the board's determination could be reviewed only for
"fraud, bad faith, or palpable error," based on
the language in the contract, with palpable error determined
to be "equivalent to bad faith." In considering
the board's decision, the court followed the rule of interpretation
that all provisions of a contract are to be given meaning
and determined that the decision did not reflect palpable
error.
Cipico
Construction Inc. v. City of New York; Supreme Court,
New York County; Judge Moskowitz; October 5, 1999.
Motion Granted Based on Lack of Notice
Contractor
sued the City of New York seeking the balance of funds allegedly
due on a contract for a plumbing job, disputed additional
work and damages due to withholding of information regarding
concealed site conditions. The project entailed the renovation
of a landmark historical building for a police station.
City moved for partial summary judgment, asserting that
plaintiff did not comply with the written notice and contemporaneous
document submission requirements of the contract. The court
granted the motion, ruling that the contractor did not comply
with the notice of claim requirements.
Pace
Plumbing Corp. v. Stein Partnership; Supreme Court,
New York County; Judge Gangel-Jacob; October 18, 1999.
No Damage for Delay Clause Held Inapplicable
Plaintiff
electrical contractor on a multi-prime project with a construction
manager alleged that defendant school district impeded and
delayed its performance of a construction contract, causing
damages. After a seven-day bench trial, the court found
that the construction manager had prepared only two coordinated
construction schedules, which were incomplete, provided
late and provided without later updates. The contract contained
a no-damage-for-delay provision, the sole remedy being a
time extension. The construction manager subsequently was
terminated for default. The court found that the no-damage-for-delay
clause was enforceable but would not bar plaintiff's claim
for damages because defendant breached a fundamental obligation
of the contract and the delays were not contemplated by
the parties when the contract was entered -- both well-recognized
exceptions to the no-damage-for-delay clause.
The
fundamental obligations breached included the failure to
schedule and coordinate the work (the construction manager's
failures being attributed to its principal, the school district),
which caused the electrical contractor's work to be performed
in an inefficient, timely economical manner. The court further
found that the delays were not contemplated by the parties.
While the court acknowledged that the contractor could only
recover damages after it provided written notice, such notice
requirement was satisfied by a letter that asserted a claim
for delay and inefficiencies, the specifics of which were
set out in attached meeting minutes, correspondence and
videotapes.
The
court's decision was less instructive on damages. The contractor
was denied recovery for extended home office overhead because
of a lack of proof that delay caused an increase in home
office overhead. No recovery was allowed for a warehouseman
and warehouse truck for similar reasons. Without further
discussion, the court set out recoverable damages for extended
site overhead, labor increases, loss of productivity, small
tools/consumables at 2 percent and profit at 10 percent.
Clifford
R. Gray, Inc. v. City School District of Albany; Supreme
Court, Albany County; Judge Maney; June 24, 1999.
Bonds' Expiration Strictly Enforced
Village
sued surety company to enforce construction performance
and maintenance bonds and to recover costs incurred due
to defective work discovered after completion of the work.
The court granted summary judgment, dismissing the action
because the bonds and the contractor's guarantee expired
one year after substantial completion, well before the discovery
of the claimed defects.
Village
of Rockville Centre v. Federal Insurance Co.; Supreme
Court, New York County; Judge Cahn; March 3, 1999.
Rejection of Delayed Claim Affirmed
Contractor,
awarded a contract to repair several train stations, challenged
respondent's dismissal of its claim for additional compensation.
After an agreed-upon design change, the contractor proposed
that no change in the contract price would be necessary.
The public owner, however, indicated that it would review
the change for a possible credit due the owner. Seven months
later, the contractor submitted a request for an increase
in price that was swiftly rejected. The trial court affirmed
the chief engineer's rejection because of the contractor's
failure to submit a notice of claim within five days.
Anthony
Marino Construction Corp. v. Nagaraja; Supreme Court,
New York County; Judge Gammerman; February 19, 1999.
No-Damage-for-Delay Clause Enforced
Subcontractor
sued contractor contending that the contractor failed to
properly coordinate the work and administer the job, causing
plaintiff to suffer delays. The court, after a three-day
trial, found in favor of contractor.
The
general conditions of the prime contract were referred to
in a simple incorporation by reference clause in the subcontract.
The court held that despite federal decisions to the contrary,
state decisions supported the incorporation of the prime
contract's no damage for delay clause, notice of claims
provisions and shortened statute of limitation. The court
found that the defense that the action was not commenced
within the shortened period provided in the prime contract
was a compulsory affirmative defense, which was not raised
in the answer and thus was waived.
As
for the 10-day notice of claims requirement, that provision
was interpreted by the court as not constituting a "condition
precedent" to recovery and, thus, did not have a preclusive
effect on the claims. In any event, the evidence supported
a finding that notice had been given both in writing and
orally.
Finally,
the court determined that the no-damage-for-delay clause
barred the subcontractor's claims because the subcontractor
failed to establish that the events complained of (failure
to coordinate deliveries of materials required for the subcontractor
to perform its erection operations) were uncontemplated
by the parties or fell into any of the other three recognized
exceptions to application of the clause set down by the
Court of Appeals in Corinno Civetta Construction Corp.
v. City of New York, 67 N.Y.2d 297, 502 N.Y.S.2d 681,
493 N.E.2d 905 (1986). Furthermore, plaintiff failed at
trial to prove damages because of the lack of expert testimony,
the failure of the job foremen to testify and the lack of
evidence from daily logs, which were not admitted into evidence.
Burt
Welding & Automotive Repair v. U.W. Marx Inc.; Supreme
Court, Albany County; Judge Maney; January 6, 1999; aff'd
707 N.Y.S.2d 548 (3rd Dept. 2000).
If you would like to receive legal reports and updates
more quickly, by e-mail, click
here and fill out the mailing list form.
For more information about the issues covered in this report, please contact Richard P. Dyer in our New York office at 212-895-2117 or at rpdyer@thelen.com or contact your Thelen attorney. For more information about Thelen's Construction and Government Contracts Department, click here.

©2000 Thelen Reid Brown Raysman & Steiner LLP
|